I've seen the contractor doing the 25th street south project working both at night and weekends.
I've seen the contractor doing the 25th street south project working both at night and weekends.
37 days, not sure if that is from the date in Sept , or from now. The panel decided that weather was not an option, blaming it on utilities, well what about poor panning.
Went to subway at 1215 today I was the only vehicle in the drive through. Masters construction, bad for business, good for a quick lunch
http://www.inforum.com/content/fargo...avenue-project
Houston Engineering recommended 37 days. Master asked for 31.5. It is from the original finish date of Sept 15.
My question is how much are the delays costing, and who is paying if the Master gets no penalty....
.
17X National Champions: 65, 68, 69, 83, 85, 86, 88, 90, 11, 12, 13, 14, 15, 17, 18, 19, 21
Join the Green and the Gold Collective to take Bison football to the next level. Starts at $10 a month
The Green and The Gold Collective is excited to announce our #DriveToFive membership campaign. The goal of this campaign is to get to 500 monthly members. Reaching this goal will help us provide financial support to NDSU student athletes, including every returning member of the football team that saw action on the field last year!
https://thegreenandthegold.com